New Power Projects taken up by RVUN for Commissioning by Year 2013-14
|
| S. No . |
NAME OF UNIT |
CAPACITY |
EXPECTED DATE OF SYNCCHRONISATION |
OPERATION OF UNIT ON SUSTAINABLE LOAD/COAL FIRING |
| 1 |
CHHABRA TPS STAGE II (UNIT-5) |
660 MW |
Sep. 2013 |
30.11.2013 |
| 2 |
CHHABRA TPS STAGE II (UNIT-6) |
660 MW |
March 2014 |
30.05.2014 |
| 3 |
SURATGARH TPS STAGE V (UNIT- 7) |
660 MW |
Sep. 2013 |
30.11.2013 |
| 4 |
SURATGARH TPS STAGE V (UNIT- 8) |
660 MW |
March 2014 |
30.05.2014 |
|
TOTAL |
2640 MW |
|
|