New Power Projects taken up by RVUN for Commissioning by Year 2013-14
S. No .
NAME OF UNIT
CAPACITY
EXPECTED DATE OF SYNCCHRONISATION
OPERATION OF UNIT ON SUSTAINABLE LOAD/COAL FIRING
1 CHHABRA TPS STAGE II (UNIT-5)
660 MW
Sep. 2013
30.11.2013
2 CHHABRA TPS STAGE II (UNIT-6)
660 MW
March 2014
30.05.2014
3 SURATGARH TPS STAGE V (UNIT- 7)
660 MW
Sep. 2013
30.11.2013
4 SURATGARH TPS STAGE V (UNIT- 8)
660 MW
March 2014
30.05.2014

 

TOTAL
2640 MW

 

 

 

FUTURE PROJECTS

Gas based Power Plant Dholpuer Stage II

330 MW

Coal based Power Plant Suratgarh unit 9-10(Super Critical) 1320 MW
Coal based Power Plant Kalisindh Unit 3-4 (Super Critical) 1320 MW
Gas based Power Plant Ramgarh

160 MW

Coal based Power Plant Banswara(Super Critical) 1320 MW