Kalisindh Thermal Power Project, Jhalawar

The site of Kalisindh Thermal Power Project is located in Nimoda, Undal, Motipura, Singharia and Devri villages of Tehsil Jhalarapatan, Distt. Jhalawar. The proposed capacity of coal based Thermal Power Project is 1200 MW. The project site is about 12 km from Jhalawar (Distt. Head quarter ) and NH-12 .It is 2km from state highway No.19 and 8 km from proposed RamganjMandi - Bhopal broad gauge rail line.

                         The site selection committee of Central Electricity Authority has visited the Nimoda and its adjoining villages of Jhalawar Distt. and site was found techno-economical feasible for setting up of a Power Project. The Govt. of Raj. have included that project in 11 th five year plan. The estimated revised cost of the project is Rs.7723 Crores. M/s. TCE Bangalore has been appointed as the technical consultant for the project. The state irrigation department has alloted 1200 mcft water for the project from proposed Kalisindh dam. The origin of the Kalisindh river is from northern slop of Vindya Mountains. The river enters from MP to Rajasthan near village Binda. After flowing 145 km in Rajasthan, the Kalisindh river merges in Chambal river near Nanera village of Distt.Kota. Its catchment area is about 7944 sq.km in Jhalawar & Kota Distt. The existing Dam is located at Bhawarasa village, primarily for P.H.E.D. purpose is being uplifted for providing a storage of 1200mcft water for this power project.

The GOR has allotted 842 bigha Government land and acquired 1388 bigha private khatedari land for the thermal project .Phase-1 will be constructed on 1400 bigha land only..
          EPC contract has been awarded to M/s. BGR Energy System Chennai on dt.09.07.2008. Total project cost is Rs.7723Crores (Revised).

                             Ministry of Coal, Govt. of India has allotted ‘Paras east and Kanta basin ‘coal blocks to RVUN in Chhatisgarh state. The RVUN has formed new company under joined venture with M/s. Adani Enterprises for mining of coal blocks and new company started the work. Annual coal requirement for the project is 56 Lacs TPA.
Progress Status as on 31.05.13

Unit#I
Commissioning activities for Rolling and Synchronization of this 600 MW commenced from April’2013, Steam Blowing, Turbine Box-up, Barring Gear etc. have been achieved till date. The Rolling and Synchronization was completed on dt.30 May 2013 on oil. The erection work of Coal Mills, Coal Handling System, Ash Handling System is in progress, the unit is scheduled to synchronized on designated fuel i.e. Coal prior to 31st July 2013.

The Rail Linking between serving station i.e. Jhalawar City to KaTPP Plant is also in progress for receiving of coal by rail, expected to be completed in the mid of July’2013.

The water supply for the 2x600 MW Kalisindh Super Thermal Power Project is from proposed Kalisindh Dam near village Bhanwarasi. This dam is being constructed by Water Resources Department, GoR. The cost of the dam is being born by RRVUNL, the construction of dam is in full swing and expected completion of dam is June’2014. However the contingency arrangement have been made by raising the height of existing anicut situated near the Kalisindh Dam.The mechanical work of Water Conductor System i.e. Construction of Intake Well, Erection of Pumps, Laying of Pipeline from Kalisindh Intake Well (situated at Kalisindh Dam Site) to KaTPP plant have been completed.
Unit#II
The erection work of Boiler for this unit have been completed. The erection work of Turbine, Generator and its auxiliaries is in advanced stage. The Turbine Box-Up, Oil Flushing, Steam Blowing and Turbine Barring Gear is scheduled to be completed by 31.08.2013. The Rolling and Synchronization of the unit is scheduled on 30.11.2013 on coal.

Salient Features

Project

Kalisindh Super Thermal Power Project Jhalawar

Capacity

1200 MW(2x600 MW)

Project Site

Village-Undel, Motipura, Nimoda, Singhania & Deveri of Tehsil Jhalarapatan, Distt. Jhalawar

Project Location

The project site is about 12 km from NH-12, 2km from state highway and 8 km from proposed RamganjMandi - Bhopal broad gauge rail line.

Land Area

2230 Bigha/564 Hq. (1400 bigha/350 Hq. in I stage)

Water source and quantity

Dam on Kalisindh river. 3400 CuM/ Hrs.

Fuel Source

Main Fuel- Coal from captive coal blocks (Paras east and kanta Basin in Chhatisgarh state)

Secondary Fuel- FO/HSD.

Quantity of Fuel (at 80% PLF)

Coal-56 Lacs TPA

FO/HSD-13000-14000 KL/A

Electro Static Precipitator

99.98 % Capacity

Stack Height

275 Mtr.

Estimated revised Cost

Rs.7723 Crores

Synchronization Date

Unit-I 30 May 2013 (on oil) achieved

Unit-II September 2013 (on oil)

 
Important Milestone for Unit-1/2 & Common System
dfujhdf
SI NO. Activity As per L-2 Sch(Unit#1) Actual Date Anticipated As per L-2 Sch.(Unit#2) Actual Anticipated
01 Boiler Civil Works Start 30.12.08 24.01.09   11.03.09 23.03.09 -
02 Boiler Erection Start 14.09.09 23.10.09   02.12.09 26.03.10 -
03 Boiler Drum Lifting 01.03.10 19.05.10   20.05.10 14.08.10 -
04 Boiler Hyd. Test (non-Drainable) 07.12.10 08.04.11   24.01.11 15.12.11 -
05 Boiler Light Up 12.03.11 30.12.12   07.06.11 - 31.08.13
06 SBO 19.05.11 26.03.13   10.08.11 - 30.09.13
07 Condenser Erection Start 03.04.10 27.11.10   24.06.10 25.08.11 -
08 TG Erection Start 23.06.10 20.12.10   31.08.10 25.08.11 -
19 TG Box Up (Final) 31.03.11 31.01.13   10.06.11 - 28.08.13
11 TG Oil Flushing 17.05.11 25.01.13   27.07.11 - 25.08.13
11 Turbine on Barring Gear) 27.05.11 03.02.13   06.08.11 - 31.08.13
12 Synchronization (on Oil) 14.06.11 30.05.13   05.09.11 - 30.09.13
13 Coal Firing 19.07.11 - 31.07.13 10.10.11 - 30.11.13
14 Full Load 07.10.11 - 30.09.13 06.01.12 - 31.12.13

 