CHHABRA THERMAL POWER STATION

* Chhabra Thermal Power Station is the coal based Electricity Generating Power Plant of Rajasthan.

LOCATION

Chhabra Thermal Power Station is located at 22km from Chhabra, near village Chowki Motipura, Tehsil Chhabra, Distt. Baran (Rajasthan).

SANCTION OF SCHEMES (STAGE-I to V)

Phase
Unit No.
Capacity(MW)
Cost(Rs.Crore)
I
I & II
2x250
2820
II
III & IV
2X250
2991

OPERATIONAL PARAMETERS

Year
Gen(MU)
PLF(%)
SPCFC OIL CONSUMPTION
AUX. CONSUMPTION
2009-2010
246.92
22.61
--
--
2010-2011
1227.28
56.04
8.37
9.78
2011-2012
1998.74
70.50
3.15
11.60
2012-2013(Upto Feb.13)
2598.86
64.88
2.213
10.75

Project Highlights:

(1)
Planned capacity
2320MW
(2)
Location
Near village Chowki Motipura, Tehsil Chhabra, Baran District
(3)
Site Features
Gently sloping 400M – 390M
Extent of Area : About 1100 acres
Site Elevation : 400M above MS(Highest Flood level 385M)
Uninhabited Site
No major township or industries in the vicinity
Well connected to State Highway – 51
Well connected to West Central Railway line (Bina-Kota
(4)
Primary Fuel
Coal from South Eastern/Northern Coal fields (Near Korba)
Calorific value : 3500K Cal/kg)
Coal requirement : 2.5MTPY for 500MW
5.0MTPY for 1000MW
(5)
Water
Source : (i) From nearby Parvati River
(ii) From nearby Bethali Dam
Water Requirement : 70,000 Cu.m/day (15.5MGD)
(6)
Power Eqation
400kV/220kV Switchyard with Interconnecting Transformers
(7)
Environmental Issues
Liquid effluent: Zero discharge concept will be adopted. Complete effluent water will be treated re-used.
Emission levels (Particulars, SO X, NO X): will be maintained well within the statutory stipulations. 250M tall common chimney for 2 units.
Thermal Pollution: Nil
Noise Pollution levels: Will be maintained well within the statutory stipulations
Solid Waste management: 100% utilisation of fly ash for commercial utilization.

SUPER CRITICAL UNITS 5 & 6

(1)
Proposed Capicity
2x660 MW
(2)
Location
Near village Chowki Motipura, Tehsil Chhabra, Baran District
(3)
TOTAL PLANT AREA
709 HECTARES
(4)
PROJECT COST
RS. 7920 CRORES
(5)
FUEL
PRIMARY FUEL: COAL
SECONDARY FUEL : HSD / HFO
(6)
FUEL REQUIREMENT
6.5 MTPA
(7)
SOURCE OF WATER :
Lashi, Parwan Irrigation Project
(8)
WATER ALLOCATION
1570 mcft
(9)
STACK
Twin Flue Stack (275Meter)
(10)
NEAREST RAILWAY STATION
CHOWKI MOTIPURA

GAS BASED UNITS

(1)
Proposed Capicity
3x110 MW
(2)
Location
Near village Chowki Motipura, Tehsil Chhabra, Baran District
(3)
TOTAL PLANT AREA
67 Acres
(4)
PROJECT COST
RS. 1320 CRORES
(5)
FUEL
PRIMARY FUEL: Liquefied Natural Gas
(6)
FUEL REQUIREMENT
1.70 MMSCMD
(7)
SOURCE OF WATER : Parwan DAM
(8)
WATER ALLOCATION 10 CUSEC (315 mcft)
(9)
STACK 70 Meter
(10)
NEAREST RAILWAY STATION
CHOWKI MOTIPURA

HIGHLIGHTS :-

1. Administrative & Financial approved accorded on 02.03.2009.

2. Land Acquisition completed.

3. Water allocation has been made.

4. MOEF Clearance awaited.